Can you move the completion date to an earlier date?

On an ECC project, if we have had compensation events that have moved the completion date out from the original completion date and then we later omit works that cause planned completion to move back, how is this to be assessed in terms of time and money? Answer ECC...

read more

Acceleration

We are using the NEC3 Engineering and Construction Contract (ECC) option A (priced contract with activity schedule). As project manager, we are close to accepting a quotation for acceleration under clause 36. How will we assess the monthly assessments to include the...

read more

What has completion to do with the completion date?

It is a requirement under the NEC3 Engineering and Construction Short Contract (ECSC) that completion is when all works have been completed in accordance with the works information and are free from any defects which would prevent the employer from using the works and...

read more

Recourse for a poor estimate

We are involved in a contract where the contractor has been appointed on an ECC option E (cost reimbursable contract). The contractor provided an estimate of costs which was incorporated into the contract, but it has become evident that the contractor’s initial...

read more

Forecasting the price for work done to date

We are using ECC option C (target contract with activity schedule). ECC, clause 11.2(29) states the price for work done to date is the total defined cost which the project manager forecasts will have been paid by the contractor before the next assessment date, plus...

read more

When is a subcontractor not a subcontractor?

In our NEC3 Engineering and Construction Contract (ECC) using option C (target contract with activity schedule), the contractor has a plant hire agreement for the provision of certain mechanical plant (which is of course ‘Equipment’) and different fees arise for...

read more

Using the activity schedule to assess compensation events

I am the project manager on a project using ECC option A. We are in the process of agreeing the quotation for a compensation event to delete items of work from the contract.   The items have prices in the activity schedule.  Why would the quotation not be simply the...

read more

Changing decisions on rejected compensation events

We have a compensation event time bar query. The contactor has notified a number of compensation events within the 8 week time bar stipulated within the ECC.  Some of these have been rejected as they were deemed to not be compensation events given the information...

read more

Reviewing contractor design

We understand the ECC stipulates a period of 3 weeks for the review of fabrication drawings arising from a contractor-designed portion. As project manager we would interpret this to mean that a particular drawing revision should be reviewed with 3 weeks.  However,...

read more

Deciding the retention free amount

In using ECC with option X16 retention, can you advise on how the retention free amount is calculated? Answer The contract term ‘retention free amount’ is in italics.  That means it is an identified term (see clause 11.1) and the amount is therefore identified in the...

read more

FS Members Area

Access the members area:
frameworks-scotland.../members

Information request

If you have any queries about Frameworks Scotland 3 please complete our enquiry form.